S. No.Name of the ContractClient NameScope of workCompletion
1Construction of Ministry of Education
& Higher Supreme Health Council
Diplomat Group
Cladding Works2018
2QP District ProjectBouygues Batiment Int’l. Midmac
Contracting Al Jaber Engineering-JV
Aluminium Cladding Works2017
3Gasal RL W1-8 ProjectMedgulf Construction Co.
Hot Insulation work2015
4BARZAN Onshore Project RaslaffanDescon Engineering
Insulation Works2015
5BARZAN Onshore Project RaslaffanJGCInsulation Works2015
6Laffan DHT ProjectQconInsulation works2014
7Plateau Maintenance Project (PMP)Descon Engineering
Insulation Works2014
8Qafco-6 ProjectHyundai Engineering & Construction
Insulation Works2013
9Qafco-5 ProjectHyundai Engineering & Construction
Insulation and Scaffolding Work2012
10Pearl GTL ProjectJGC/ CCIC
Insulation Works2011
11Pearl GTL Project – C4Hyundai Heavy Industries
Insulation Works2011
12Qatargas 3 & 4 Expansion Project
(Trains-6 &7) Utilities & Offplot Area
Gama QatarHot & Cold Insulation Works2010
13Qatargas 3 & 4 Development
Project (Trains-6 &7) Process Area
Chiyoda / CCIC

Cold Insulation2010
14QAFCO-5 ProjectCB&IInsulation and Scaffolding Work2010
15Qatargas-II Development Project
( Train-4 & 5)
Chiyoda / CCIC

Cold Insulation Works2009
16Laffan Refinery Project Phase 1,
Qatargas
DaewooInsulation Works2009
17Ras Laffan Onshore Expansion
Project Train -5
Chiyoda / CCIC
Cold Insulation2007
18Al Khaleej Gas Plant ProjectChiyoda / CCIC
Cold Insulation Fireproofing & Scaffolding Works2005
19Ras Laffan Onshore Expansion
Project Train-4
Chiyoda / CCIC

Insulation, Fire proofing, Refractory & Scaffolding Works2005
20Ras Laffan Onshore Expansion
Train -3
Chiyoda / CCIC
Insulation Works2004